Title: Recommended FY 2027 Wake Transit Work Plan Steven Mott, MPO Staff
Attachments: 1. Staff Report, 2. Recommended FY27 Wake Transit Work Plan, 3. Recommended FY27 Wake Transit Work Plan Executive Summary

Title

Recommended FY 2027 Wake Transit Work Plan

Steven Mott, MPO Staff

 

Body

MPO Staff will present on the TPAC-recommended FY 2027 Wake Transit Work Plan. The recommended FY27 Work Plan includes approximately $170.7 million in transit investments for FY27 (July 1, 2026 - June 30, 2027) across operating [$78.5M] and capital [$92.2M] expenditures. Key elements of this year’s annual Work Plan provide continued bus network expansion including new and improved routes, allocations for Community Funding Area Program projects totaling approximately $6.2M, $23.8M towards regional rail efforts, and $36.4M in bus infrastructure investments. The breakdown of the FY27 investments is as follows:

Operating Investments: $78.5 million

o                     Total Bus Operations: $70.3 million

                     New bus operations and improvements: $6.5 million

                     Continuation of existing services: $59.1 million

                     Community Funding Area Program: $4.7 million

o                     Transit Plan Administration: $7.5 million

o                     Tax District Administration: $679,167

 

Capital Investments: $92.2 million

o                     Bus Infrastructure: $36.4 million

o                     Vehicle Acquisition: $15.0 million

o                     Bus Rapid Transit: $14.2 million

o                     Capital Planning: $1.3 million

o                     Community Funding Area Program: $1.5 million

o                     Regional Rail: $23.8 million

 

The Work Plan is fiscally constrained and budgets $157.9 million in revenue from local funding sources, supplemented by $12.8 million allocated from the prior year’s capital fund balance.

 

This item is information-only for the May 14, 2026, TCC meeting. The CAMPO Executive Board will review this item at their May 20, 2026 meeting. The TCC will review this item again, along with the summary of the 14-day public comment period occurring from May 6-20, 26, at their June 4, 2026, meeting, where they will be asked to recommend the FY 2027 Wake Transit Work Plan to the CAMPO Executive Board for adoption. The CAMPO Executive Board will conduct a public hearing and be asked to take action at their June 17, 2026, meeting.

 

Requested Action: Action Receive as information