Skip to main content

File #: REP 16-230    Version: 2 Name:
Type: Informational Report Status: Filed
File created: 10/24/2016 In control: Executive Board
On agenda: 11/16/2016 Final action:
Title: Wake Transit Plan Implementation Update and Presentation of FY 2017 Wake Transit Work Plan Bret Martin, MPO Staff
Indexes: FTA, Transit
Attachments: 1. FY 2017 Wake Transit Work Plan - TPAC Rec

Title

Wake Transit Plan Implementation Update and Presentation of FY 2017 Wake Transit Work Plan

Bret Martin, MPO Staff

 

Body

As noted in previous Executive Board meetings, the Wake County Transit Planning Advisory Committee (TPAC) held multiple meetings during the summer and into the fall to develop its operational structure, formats for its ongoing work products, and technical programming and budgeting recommendations related to Wake Transit Plan implementation. The TPAC is currently in the process of developing the FYs 2017 and 2018 Wake Transit Work Plans for recommendation to the CAMPO Executive Board and GoTriangle Board of Trustees. The TPAC took action on a recommendation of the FY 2017 Wake Transit Work Plan at its November 9th meeting. Following is a draft schedule for the CAMPO Executive Board’s and GoTriangle Board of Trustees’ consideration of the recommended FY 2017 Wake Transit Work Plan:

 

Action

Date

TPAC Recommendation to Governing Boards

November 9, 2016

Draft Presented to CAMPO Executive Board as Information Only

November 16, 2016

GoTriangle Board of Trustees Consideration of Approval

December 14, 2016

CAMPO TCC Consideration of Recommendation to Executive Board

January 5, 2017

CAMPO Executive Board Consideration of Approval

January 18, 2017

 

As noted in the draft schedule, the TPAC-recommended FY 2017 Wake Transit Work Plan will be presented to the Executive Board at its November 16th meeting as information only and is proposed to return to the Executive Board for final consideration of approval after being reviewed by the TCC in January. A draft of the FY 2018 Work Plan will remain in a developmental state until May 2017, when it is scheduled to move forward for consideration by the governing boards.

 

One major component of annual work plans is the formal agreement structure within which all beneficiaries of tax district proceeds will be expected to operate in their execution of Wake Transit Plan implementation activities. In addition to a presentation of the FY 2017 Wake Transit Work Plan, staff will provide an overview at the Executive Board meeting of this structure and what participating agencies and municipalities can expect with regard to these agreements as the FY 2018 Work Plan is developed. Staff will also provide an overview of other ongoing Wake Transit Plan implementation activities, including the on-call transit planning services task work program for FY 2017.