Title
North Falls Lake Area Study
Gaby Lawlor, MPO Staff
Body
The North Falls Lake Area Study was funded in the FY25 UPWP. The Request for Proposals was open from October 28, 2024 to December 6, 2024. Four proposals were submitted and after scoring each, a proposal review team met on December 13, 2024 and selected a preferred candidate. The proposal review team included representatives from CAMPO, Granville County, Wake County, and NCDOT. After working with the consultant to refine a scope to accomplish the goals of the study, and successfully negotiating fees for the study, the contract is now ready for execution. The fee to complete the scope of work is $289,194.79.
Requested Action: Action Review and approve the draft contract and final scope for the North Falls Lake Area Study, and authorize CAMPOs Executive Director to execute the final contract.