CAMPO has been tasked with updating the Bus Plan Project Prioritization Policy (PPP) as part of the Wake Bus Plan process led by GoTriangle. The PPP is a critical tool needed to establish each transit provider’s shortrange transit investment plans. The purpose of the Wake Bus Plan PPP is to be a decision-making framework that provides: transparent and easily understandable process for making choices between competing investment needs; guidance on the development of the bus service and capital investment plan prepared through the Wake Bus Plan; and an optional process that may be used by the TPAC to adjust bus service and the capital investment program outlined by the Multi-Year Bus Service Implementation Plan (MYBSIP) to reflect changes in available funds, new or substantially modified project requests, or other needs in the region.

 

The PPP was released for public review from November 9th - 23rd. Additionally, it was recommended for adoption to the Wake Transit Governing Boards by the TPAC as their December 14th meeting. During this presentation, CAMPO staff will review the engagement summary and details of the policy for TCC consideration. No changes have been made to the Wake Bus Plan PPP since it was brought to the TCC as an information item.

 

Requested Action:Action Recommend adoption of the updated Wake Bus Plan Project Prioritization Policy to the CAMPO Executive Board.