File #: TIP 16-253    Version: Name:
Type: TIP Item Status: Regular Business
File created: 7/25/2016 In control: Executive Board
On agenda: 8/17/2016 Final action:
Title: TIP PROJECT I-5710 - RAMP METERING on I-540 Battle Whitley/Jamille Robinson - NCDOT staff
Indexes: Ramp Metering, TIP
Attachments: 1. I-5710 Ramp Metering
Title
TIP PROJECT I-5710 - RAMP METERING on I-540
Battle Whitley/Jamille Robinson - NCDOT staff

Body

The North Carolina Department of Transportation (NCDOT) completed an in-depth analysis of traffic operations along I-540 based on the Ramp Metering Study completed in 2013. Based on the study NCDOT determined that implementation of on-ramp signals for congestion relief (i.e., "ramp metering," the use of stop-and-go signals to regulate the flow of on-ramp traffic when merging onto the freeway) is a viable option to address increasing congestion and improve efficiency on this major freeway. Based on this analysis, four westbound ramps along I-540 have been selected as North Carolina's first on-ramp signal sites.

The NCDOT State Transportation Improvement Program (STIP) Project I-5710 is the installation of the state's first ramp metering signals on four existing on-ramps to westbound I-540 in the City of Raleigh in Wake County at:
? Exit 14 - Falls of Neuse Road (SR 2000).
? Exit 11 - Six Forks Road (SR 1005)
? Exit 9 - Creedmoor Road (NC 50)
? Exit 7 - Leesville Road (SR 1839)

Construction activities will involve the addition of pavement to some ramps, extension of guardrail, additional signing and pavement markings, and installation of ramp metering signals and Intelligent Transportation Systems (ITS) elements (CCTV cameras, fiber-optic communications cable, and server and communications equipment). All work will occur within the existing right-of-way, with some minor pavement widening and extension of existing ramp lanes. The on-ramp signals will be operational during peak times (rush hour) and activated through sensors when congestion is present.

The project is scheduled for completion within Fiscal Year 2016 at an estimated total cost of $1.1 million. It is anticipated that the proposed on-ramp signals will be operational in spring 2017.
"Ramp metering" also known as "on ramp signals" is a traffic management concept and form of Intelligent T...